Repair coming for Greater Victoria sewage treatment plant, CRD says
It cost $775 million to build and took five years to complete. It’s the CRD’s sewage treatment plant, and so far, it’s not functioning as it should.
“One has to wonder what we got for $800 million,” said Hugh Stephens, vice chair of the Mount Work Coalition.
The plant was touted as the CRD’s sewage solution. Instead of pumping treated waste into the ocean, the region’s sewage would be turned into tiny pellets and sent to the Lafarge cement plant in Richmond, to be burned as an alternative to coal.
“Apparently, the anaerobic digester’s not working; the dryer’s not working,” said Stephens.
Right now, the pellets don’t meet Lafarge’s specifications, as they are not the right size, so the CRD had to do something with the biosolids the plant was producing.
“Right now, it’s just being dug in trenches and put into the landfill,” said Stephens.
Neighbours of the facility at Hartland Landfill have concerns about that.
“If there’s anything that goes wrong, Todd Creek is done, Saanich Inlet is done,” said Stephens. “You know, there have been issues in the past with leachate coming out.”
Mike Hicks sits on the CRD board. He admits there are issues with the plant.
“You know, all my life I’ve had engines, outboards,” said Hicks. “I’ve built fishing lodges, and once in a while I just got a lemon and no matter what I did to it, I just couldn’t get it to work. I really hope this isn’t one of those lemons.”
He’s confident that a fix will come, but in the meantime he feels for the people living and visiting the area around Hartland Landfill.
“The poor people of Willis Point are enduring this terrible stench as they do this, and hikers,” said Hicks. “It’s not good and it can only get better.”
The CRD says a fix is on it’s way.
Glenn Harris, senior manager of the CRD’s Environmental Protection Division, describes the issue as a mechanical one.
“We’re simply going to get a sieve in place where we can actually make sure that we can shake through the pellets and get them down to a size that Lafarge, the cement facility, can handle,” Harris said. “That’s a mechanical solution and we have that on order and we expect that to be in place in the next few weeks.”
Because of the project agreement, it won’t cost taxpayers any more money.
“(The contractors who did the work are) obligated and they have the liability to resolve the issues with the plant,” said Harris. “So they have an incentive to fix this as soon as possible.”
The CRD is hoping to have the problem resolved and to begin shipping bio-solids to Richmond this summer.
CTVNews.ca Top Stories
'They needed people inside Air Canada:' Police announce arrests in Pearson gold heist
Police say one former and one current employee of Air Canada are among the nine suspects that are facing charges in connection with the gold heist at Pearson International Airport last year.
House admonishes ArriveCan contractor in rare parliamentary show of power
MPs enacted an extraordinary, rarely used parliamentary power on Wednesday, summonsing an ArriveCan contractor to appear before the House of Commons where he was admonished publicly and forced to provide answers to the questions MPs said he'd previously evaded.
Leafs star Auston Matthews finishes season with 69 goals
Auston Matthews won't be joining the NHL's 70-goal club this season.
Trump lawyers say Stormy Daniels refused subpoena outside a Brooklyn bar, papers left 'at her feet'
Donald Trump's legal team says it tried serving Stormy Daniels a subpoena as she arrived for an event at a bar in Brooklyn last month, but the porn actor, who is expected to be a witness at the former president's criminal trial, refused to take it and walked away.
Why drivers in Eastern Canada could see big gas price spikes, and other Canadians won't
Drivers in Eastern Canada face a big increase in gas prices because of various factors, especially the higher cost of the summer blend, industry analysts say.
Doug Ford calls on Ontario Speaker to reverse Queen's Park keffiyeh ban
Ontario Premier Doug Ford is calling on Speaker Ted Arnott to reverse a ban on keffiyehs at Queen's Park, describing the move as “needlessly” divisive.
'A living nightmare': Winnipeg woman sentenced following campaign of harassment against man after online date
A Winnipeg woman was sentenced to house arrest after a single date with a man she met online culminated in her harassing him for years, and spurred false allegations which resulted in the innocent man being arrested three times.
Woman who pressured boyfriend to kill his ex in 2000s granted absences from prison
A woman who pressured her boyfriend into killing his teenage ex more than a decade ago will be allowed to leave prison for weeks at a time.
Customers disappointed after email listing $60K Tim Hortons prize sent in error
Several Tim Horton’s customers are feeling great disappointment after being told by the company that an email stating they won a boat worth nearly $60,000 was sent in error.