'A perfect storm': Vancouver Island construction industry warns of significant delays and cost overruns
The success of Vancouver Island's construction industry might also be its post-pandemic downfall.
"I think we have what could be considered a perfect storm," said CEO of the Vancouver Island Construction Association, Rory Kulmala.
As the demand for large-scale developments boom, especially on southern Vancouver Island, the industry says major supply concerns and labour shortages will have an impact.
"That is going to reflect in itself much longer schedules and higher costs," Kulmala told CTV Vancouver Island on Tuesday.
The construction association says building permits for commercial, multi-residential and single-family homes have climbed year-over-year for the past half decade.
This year the association expects a 30 per cent increase in permits from 2020, which would represent a record year.
Multi-residential, or condo and apartment building permits, are the hottest sector.
Victoria city staff tell CTV News that the pace of major development applications in 2021 is the highest they have ever seen.
As demand booms, an already stressed sector will no doubt bend under the immense pressure.
This week, the Greater Victoria School District announced its Victoria High School redevelopment is far behind schedule.
"The school will open in September of 2023 instead of September of 2022," said Jim Soles, manager of Major Capital Projects for SD61.
Market forces have hit the large-scale seismic upgrade hard, pushing it a year behind its projected completion date.
"Trades cannot guarantee tight schedules because of a shortage of workers and the supply chain is causing problems," said Soles.
What does this all mean for the average Vancouver Islander?
Vancouver Island's Construction Association says work will not stop, but getting things done will likely take longer and hit your wallet harder.
CTVNews.ca Top Stories
Fluid in eye cells can 'boil' if you watch the eclipse without protection: expert
Millions of people in parts of Eastern and Atlantic Canada will be able to see the rare solar eclipse happening on April 8. But they should only look up if they have proper eye protection, experts say.
He didn't trust police but sought their help anyway. Two days later, he was dead
Jameek Lowery was among more than 330 Black people who died after police stopped them with tactics that aren’t supposed to be deadly, like physical restraint and use of stun guns, The Associated Press found.
CRA no longer requiring 'bare trust' reporting in 2023 tax return
The Canada Revenue Agency announced Thursday it will not require 'bare trust' reporting from Canadians that it introduced for the 2024 tax season, just four days before the April 2 deadline.
Being harassed at work? What to consider when deciding what to do next
If you've been the victim of workplace harassment, it can be difficult to feel you're not alone - and even more difficult to know where to go with a complaint.
Ontario urges mpox testing amid spike in cases
Ontario health officials are urging public health units to test for mpox, the viral disease formerly known as monkeypox, amid a spike of confirmed cases in the province.
Half of Canadians support TikTok ban, with U.S. concerns 'trickling' north: poll
A new poll indicates 51 per cent of Canadians support banning the social media app TikTok, after a U.S. bill aiming to do just that passed in the House of Representatives.
More unauthorized products for skin, sexual enhancement, recalled: Here are the recalls of this week
Health Canada and the Canadian Food Inspection Agency recalled various items this week, including torches, beef biltong and unauthorized products related to skin care and sexual enhancement.
Where is the worst place for allergy sufferers in Canada?
The spring allergy season has started early in many parts of Canada, with high levels of pollen in some cities already. Experts weigh in on which areas have it worse so far this season.
Do these exercises for core strength if you can't stomach doing planks
Planks are one of the most effective exercises for strengthening your midsection, as they target all of your major core muscles: the transverse abdominis, rectus abdominis, external obliques and internal obliques. Yet despite the popularity of various 10-minute plank challenges, planking is actually one of the most dreaded core exercises, according to many fitness experts.